STATE OF MICHIGAN
DEPARTMENT OF ENVIRONMENTAL QUALITY
OFFICE OF ADMINISTRATIVE HEARINGS
SUBJECT: Part 301, Inland Lakes and Streams and Part 353, Sand Dunes Protection
and Management, of the Natural Resources and Environmental Protection Act, 1994
PA 451, as amended (NREPA)
Petition of Dune Harbor Estates, LLC
File No. 00-61-0039-P
PROPOSAL FOR DECISION
Dated: February 24, 2004 Richard A. Patterson
Administrative Law Judge
This contested case involves an application of Dune Harbor Estates LLC (Dune
Harbor) that has two components. The first is for a permit under Part 301 (MCL
324.30101 et seq.). Specifically, the application proposes to install a water
level control device in an artificial body of water that has resulted from sand
mining operations conducted by Dune Harbor's related entity, Nugent Sand. The
second component involves an application for special exception under Part 353
(MCL 324.35301 et seq.) to place on outfall in a critical dune area on the shore
of Lake Michigan.
During the application review process the proximity of the outlet to Lake Michigan
gave rise to consideration of the outfall under the regulatory provisions of
Part 325, Great Lakes Submerged Lands, of the NREPA (MCL 324.32501 et seq.).
However, as is apparent from the evidence summarized and analyzed below, none
of the proposed activity is to be conducted below the ordinary high water mark
(OHWM) of Lake Michigan. In fact, in its post-hearing pleadings, the Geological
and Land Management Division (GLMD) abandoned its argument that a Part 325 permit
was required.
JURISDICTION
Part 301 grants the right to a contested case hearing to a person who "is
aggrieved by any action or inaction of the department." MCL 324.30110(2).
Part 353 grants a similar right to a person who "is aggrieved by a decision
of the department in regard to the...denial of a...special exception."
MCL 324.35305(1). Dune Harbor exercised its right under these statutory provisions
by timely filing a petition for a contested case hearing. Consistent with these
provisions the hearing was conducted in the manner provided for in the Michigan
Administrative Procedures Act, 1969 PA 306, as amended. MCL 24.201 et seq.
PROPERTY RIGHTS PRESERVATION ACT CONSIDERATION
Pursuant to the Property Rights Preservation Act, 1996 PA 101, MCL 24.421, et
seq., in formulating this Proposal for Decision (PFD) the undersigned has reviewed
the Takings Assessment Guidelines and considered the issue of whether this government
action constitutes a constitutional taking of property.
PARTIES
Dune Harbor is represented by William C. Fulkerson and Rodrick W. Lewis, Warner,
Norcross and Judd, LLP. Dune Harbor presented the testimony of Robert Chandonnet,
President of Nugent Sand and owner of Dune Harbor; John Nevedal, Vice President
of Operations, Nugent Sand; David A. Stebbins, Landscape Architect, and Development
Director for Dune Harbor Development; Scott R. Bazinet, Lowe Construction Company;
Alan W. Hinks, hydrogeologist; Arthur Nash Jr., former Deputy Director, Department
of Environmental Quality (DEQ); Thomas R. Bennett and Stuart Kogge, principals
of Wetland and Coastal Resources; and Dennis Dunlap, registered civil engineer
and licensed land surveyor.
The professional staff of the GLMD is charged with the day-to-day implementation
of Parts 301 and 353. Representing the GLMD is John Fordell Leone, Department
of Attorney General. The GLMD presented the testimony of Douglas Daniels, field
inspector for the sand mining program administered by the GLMD; Michelle Hohn,
James Fortney, and Mathew Warner, Environmental Quality Analysts, GLMD; Guy
A. Meadows, Ph.D., Director, University of Michigan Ocean Engineering and Marine
Hydrodynamics Laboratory; and Alan F. Arbogast, Ph.D., Associate Professor of
Geography at Michigan State University.
The hearing in this matter was held on July 8 through 11, and July 16 and 17,
2003. During the hearing Dune Harbor introduced 39 exhibits and the GLMD introduced
7.
Post-hearing filings consisting of written Closing Arguments, proposed Findings
of Fact and Conclusions of Law, and Responses culminated on September 22, 2003.
The proffered Findings and Conclusions were carefully reviewed and considered
in preparing this PFD. Any of those inconsistent with this PFD are rejected
as being either contrary to the evidence or law, or unnecessary for the disposition
of this matter.
STIPULATIONS
During the pre-hearing conference on April 17, 2003, the Parties stipulated
that Dune Harbor is the proper applicant for a permit. In addition, through
a Request to Stipulate filed by Dune Harbor and the GLMD's Response, the following
stipulations were entered into:
1. The two lakes on the Dune Harbor property were created from upland and authorized
under a sand mining operation permitted by the Department of Natural Resources
and DEQ permits 80-9-2 and 99-09-0083-P. The activity is also authorized by
sand dune mining permit No. Nus-LAS-A4.
2. The land which is subject to the present Part 301 permit application is within
a sand mining area authorized under permit No. Nus-LAS-109-A4.
3. The two subject inland lakes are not connected by a navigable means to navigable
waters.
4. The ordinary high water mark elevation of Lake Michigan is established at
579.8 feet, 1955 IGLD. MCL 324.32502.
While stipulations of law are not binding, In Re Finlay Estate, 430 Mich 590,
595; 424 NW2d 272 (1988), stipulations of fact are sacrosanct. Dana Corporation
v Employment Security Commission, 371 Mich 107, 110; 123 NW2d 277 (1963). See
also American National Fire Insurance Company v Frankenmuth Mutual Insurance
Company, 445 Mich 91, 93; 516 NW2d 52 (1994) (remand required where trial court
apparently refused to follow parties stipulation of facts). The Parties stipulations
in this case are factual, and as such are legally sustainable and adopted as
findings of fact. MCL 24.278.
PREVIOUS OPINIONS AND ORDERS GOVERNING THIS CASE
An Opinion and Order entered on June 24, 2003, that denied Dune Harbor's Motion
for Summary Disposition held that because the two lakes involved are not navigable
they are not impressed with the public trust. Further, it was held that as artificial
bodies of water the lakes do not vest riparian rights in their littoral owners.
Ergo, the activity proposed under Part 301 cannot adversely affect either the
public trust or riparian rights. As a result, the Part 301 review will be limited
to the remaining permitting criterion. MCL 324.30106.
Relative to Part 353, the Order held the term "critical dune area"
applies to the immediate area impacted, as opposed to the entire designated
geographical critical dune area in which the activity will occur. Finally, it
was held that the proposed outlet is not a "structure" absolutely
forbidden at any point lakeward of the crest of the first landward ridge of
a critical dune area that is not a foredune. MCL 324.35316(2). Subsequently,
the GLMD filed a Motion for Interlocutory Review with the Director seeking a
reversal of the determination that the outlet is not a "structure".
The Director denied the Motion, without prejudice, in an Order entered on July
7, 2003, but preserved the GLMD's right to raise the issue in its Exceptions.
In its post-hearing filings the GLMD invites this Tribunal to revisit the finding
on whether the proposed outlet is a structure, but offers no different facts
or legal argument to change the holding.
Lastly, the June 24, 2003, Order held that a question of fact as to the applicability
of Part 325 existed based on the GLMD's refusal to stipulate that none of the
proposed activity would be conducted below the OHWM of Lake Michigan. During
the hearing Mr. Bennett testified that none of the three designs for the rock
plunge pool would be installed below the OHWM. This testimony is confirmed by
the drawings of the three designs depicted on Exhibit P-24. The GLMD did not
offer any testimony to the contrary, and as noted acknowledges Part 325 is not
implicated in its Closing Argument. Therefore, the DEQ lacks jurisdiction under
Part 325.
FINDINGS OF FACT
Location and Nature of the Subject Property
Nugent Sand owns 440 acres upon which it has conducted sand mining activities
for over 90 years. The site is located in the city of Norton Shores in Muskegon
County, approximately 2.5 miles south of the city of Muskegon, and fronts on
Lake Michigan. An aerial photograph of the area entered as Petitioner's Exhibit
28 is illustrative. The mining operations have resulted in the formation of
two lakes. One of the lakes that will be referred to as South Lake is no longer
subject to active mining operations and has been configured pursuant to a reclamation
plan as part of the sand dune mining permit. Exhibit P-17. It is around South
Lake that Dune Harbor proposes to construct a residential development. A comprehensive
site plan for that development was formulated and approved by the city of Norton
Shores. A conceptual drawing of phase one of that project is depicted on Exhibit
P-21. This plan was predicated upon an estimated static water elevation in South
Lake of 582 to 584 feet at the cessation of mining creating a water body of
some 120 acres. However, subsequent to the cessation of mining, the water level
continued rising, ultimately reaching a level of 592 feet. As a result, the
anticipated lots fronting on South Lake would be inundated, unbuildable, and
installation of utilities and other infrastructure became problematic.
The Proposed Activity
In order to implement the approved site plan, Dune Harbor seeks a permit under
Part 301 to install a control device in the other lake on the site, which will
be referred to as North Lake. After connection of the two water bodies is completed
that device will control the level of both lakes. It is anticipated the water
level of South Lake would be drawn down to a level of 586 feet, approximately
4.76 feet below existing level. The control structure would discharge water
to a 36-inch pipe that would be bored and jacked 27 feet on average, below critical
dune topography approximately 600 feet to a rock plunge pool on the shore of
Lake Michigan. Exhibit P-23. The borders of the critical dune area, the extent
of Dune Harbor's property and the location of the proposed pipe and outflow
are depicted on map sheets created by GIS and photogrammetry by Mr. Warner of
the GLMD. Exhibits R-1, 2, and 3. The installation of the pipe and outflow is
regulated under Part 353. The discharge from that pipe was authorized under
a National Pollution Discharge Elimination System (NPDES) permit issued on February
4, 2003, by the DEQ, Water Division. The terms and conditions of that NPDES
permit are not an issue in this contested case.
The original plan for this activity is depicted in the attachments to the application
for permit and special exception entered as Exhibits P-1 and P-2. Two additional
configurations for the rock plunge pool were explored during the application
review process. See Exhibit P-24. All of these proposals and how they came to
be developed are discussed in detail later in this PFD.
The GLMD denied the application for the control device and the rock plunge pool.
As to the control device, it determined lowering the lake level would have an
adverse impact on the littoral zone. It further determined the rock plunge pool
would create a contour change and increase the risk of erosion in the critical
dune area. The GLMD also takes the position that two feasible and prudent alternatives
are available. The first would be to redesign the project to work around the
increased lake level. The second would be to place the end of the discharge
pipe underwater on the bottomland of Lake Michigan some distance from the shore.
PART 353 ANALYSIS
Part 353 embodies a regulatory scheme for land features the Legislature has
determined are of great importance. MCL 324.35302. While the statute contemplates
certain uses on these resources, specific criteria must first be met. MCL 324.35312
through MCL 324.35317. As this statute is an exercise of the authority to regulate
land use, a local unit of government has the discretion to assume the regulation
of critical dunes within its jurisdiction. MCL 324.35304. However, if a local
unit of government declines this legislative grant of authority, as is the situation
in this case, the DEQ is charged with administering the statute. MCL 324.35304(3).
Dune Harbor proposes activity within the confines of what has been designated
as a critical dune area in the "Atlas of Critical Dunes" pursuant
to MCL 324.35301(c). This requires a determination of whether the proposal falls
within the scope of following provision of Part 353:
Unless a variance is granted pursuant to section 35317, a zoning ordinance shall
not permit the following uses in a critical dune area:
***
(d) A use involving a contour change that is likely to increase erosion, decrease
stability, or is more extensive than required to implement a use for which a
permit is requested.
***
(g) A use that is not in the public interest. In determining whether a proposed
use is in the public interest, the local unit of government shall consider both
of the following:
(i) The availability of feasible and prudent alternative locations or methods,
or both, to accomplish the benefits expected from the use. If a proposed use
is 1 single family dwelling on a lot of record owned by the applicant, consideration
of feasible and prudent alternative locations shall be limited to the lot of
record on which the use is proposed. A lot of record shall not be created strictly
for the purpose of avoiding consideration of alternative locations under this
subparagraph.
(ii) The impact that is expected to occur to the critical dune area, and the
extent to which the impact may be minimized.
MCL 324.35316(1).
The previous order referred to above determined the outlet was not a structure
and is, therefore, not expressly prohibited. Although the outlet is not a structure,
it may be regulated if it is a "use". The term "use" is
defined as "a developmental...activity done or caused to be done by a person
that significantly alters the physical characteristic of a critical dune area
or a contour change done or caused to be done by a person." MCL 324.35301(j).
Thus a "use" consists of a two-part disjunctive test. The first component
of the test, significant alteration, is not defined in the statute. However,
the second part, contour change, is defined as a specified activity that "significantly
alters the physical characteristic of the critical dune area...." MCL 324.35301(a).
To determine if a "use" is at issue the proposed activity and its
effects to the natural feature must be examined. This project under any of the
various configurations involves placement of rock rip rap and metal grates and
in some plans, concrete or grout. Any of these designs would result in the replacement
of the existing sand surface with an elevated form of impervious surface. Such
an activity can only be termed a significant alteration of the dune's physical
characteristic. The same configuration constitutes a contour change as well
in that the elevation and natural slope would be altered. Therefore, based on
the record in this case I find, as a Matter of Fact:
1. The proposed activity would result in a significant alteration of the physical
characteristic of the dune.
2. The proposed activity would constitute a contour change of the dune.
Given these findings, the inquiry turns to whether it falls under one of the
seven categories in § 35316(1) that can only be performed under the authority
of a special exception. The most applicable category asks whether the activity
involves "[A] use involving a contour change that is likely to increase
erosion, decrease stability, or is more extensive than necessary...." MCL
324.35316(1)(d).
Dr. Arbogast specializes in geomorphology, or the evolution of landscapes, and
particularly eolian (wind driven) environments. He described his present research
as being virtually 90 percent focused on sand dunes in Michigan, both in the
interior of both peninsulas as well as along the coast of the Great Lakes. From
his review of materials and on-site reconnaissance, he determined the subject
dune is approximately 4,000 years old, but that the upper deposits are very
poorly developed, indicating, to him, they have existed for 200 years or less.
Specific to the location of the proposed outlet, Dr. Arbogast testified it would
be installed in the foredune complex as opposed to the barrier dune landward.
He characterized the area as inherently unstable because it is basically a sand
bar that is susceptible to wind erosion. Under current conditions of low water
levels he would expect the foredune to increase in height as the prevailing
west winds drive loose sand landward. He notes the possibility that this could
result in part of the proposed outlet being buried within 10 to 15 years. He
does not foresee any adverse effects from the proposed jack and bore installation
of the discharge pipe. In addition, his report indicates:
Construction of the riprap structure will certainly modify the low-lying foredunes,
but these dunes can easily be remodeled because they essentially consist of
small mounds of sand that will quickly be shaped into dune forms when strong
winds prevail.
***
Although I see no significant problems associated with the proposed construction
activities, I am concerned about impacts during future periods of high water
in Lake Michigan.
Exhibit R-7, pg. 4.
Under the 30 year cycle for water levels to which he ascribes, because the
last high water levels were around 1986 he would expect Lake Michigan to begin
rising in the near future, and within 15-20 years the Great Lakes will be at
or near all-time highs. When the water level of Lake Michigan reaches 580.7
feet, which it has on a number of occasions or the all time high of 582.3, water
would be within 10 feet or in contact with the structure. At that point it would
essentially act as a groin, blocking sediment on the upstream side of the littoral
drift and eroding it on the opposite side.
Dr. Meadows, a Professor of Naval Architecture, Marine Engineering, and Physical
Oceanography at the University of Michigan, began studying wave transformations
across near shore regions of the Lake Michigan shoreline as an undergraduate
student at Michigan State University. Since that time essentially all of his
work has been involved with the effect of near-shore structures on natural beaches.
He generally agreed with Dr. Arbogast's testimony, and added that if the water
level of Lake Michigan reached the highest recorded level of 582.35 and a maximum
storm surge of 1.8 feet occurred, the proposed outfall would become a shore-perpendicular
groin influencing the shoreline up to six times the length of the structure
in both directions. He calculated this area to be from 180 to 210 feet. According
to Dr. Meadows, under such conditions, which he termed a "worst case scenario",
the outfall would also eventually begin to directly impact the main barrier
dune. T., pg. 1027.
As to the discharge from the pipe, neither Dr. Arbogast nor Dr. Meadows perceived
any significant ongoing erosive impact to the shoreline. Dr. Arbogast testified
that any erosion from the low velocities of the discharge would probably create
only a slight ditch from the end of the installation to Lake Michigan, and he
would not expect substantial up or down drift changes. T., pgs. 1002-1003. Similarly,
Dr. Meadows testified he did not believe there would be any impacts to the shoreline
related to the channel that may be created from the water discharged from the
pipe. T., pgs. 1017-1018.
Dune Harbor offered the testimony of Mr. Bennett regarding the impact of the
proposed activity on the dune. Mr. Bennett is a former employee of the DEQ who
during his tenure worked as a state-wide coastal expert providing technical
review of shoreline impacts of proposed construction or nourishment activities,
as well as acting as an expert witness on coastal processes. He has been published
in this field, on occasion in conjunction with Dr. Meadows. Mr. Bennett testified
that a lake level of 582 feet on Lake Michigan has been met or exceeded only
2/10 of 1 percent since 1918. T., pg. 1102. Further, he calculated the probability
of the simultaneous occurrence of a level or 582 feet and a storm surge of 1.8
feet to be 1 in 50,000. T., pg. 1104. In respect to the opinion of Dr. Arbogast
and Dr. Meadows, he notes they based their calculations on the elevations of
the underground portion of the three designs of the outfall. In Mr. Bennett's
opinion, the proper elevation should be the point at which the outfall intersects
with the beach profile. At this elevation, the third design would have an elevation
of 586.7 feet and would not be affected even under the "worst case"
scenario offered by Dr. Meadows.
To summarize the above, both Dr. Arbogast and Dr. Meadows testified that any
beach erosion from water exiting the outfall would be minimal. They both also
acknowledged that the installation would neither increase erosion nor decrease
stability under present low water conditions. However, each is concerned with
its potential effect under higher water conditions, or what Dr. Meadows acknowledged
was a "worst case scenario". The statistics generated by Mr. Bennett
indicate that the combination of events necessary to effectuate that scenario
render it improbable. While this testimony may indicate that the concerns coming
to fruition may be remote, it cannot be ruled out and therefore, its likelihood
of increasing erosion or decreasing stability cannot be foreclosed. As to the
second prong, whether the outfall is more extensive than necessary, the record
indicates every effort has been made to engineer the system to produce the control
needed while insuring adverse effects are minimized.
Based on the above, I find that, while the installation is not more extensive
than necessary, it does, in fact, constitute a use involving a contour change
that is likely to increase erosion or decrease stability under limited circumstances.
The analysis on the extent of the project and the GLMD's contention that placing
the outflow on the bottomland of Lake Michigan constitutes a feasible and prudent
alternative ties into another category of use that requires a special exception.
Section 35316(1)(g) mandates the use be in the "public interest",
a term utilized in the context of avoidance of an impact to the resource. In
determining whether the proposed use in the public interest, § 35316(1)(g)(i)
and (ii) requires an analysis of whether a feasible and prudent alternative
location or method that provides the benefit sought exists, or whether there
is a means to minimize the effect to the resource.
Because § 35316(1)(g) is implicated, the alternatives must be addressed,
specifically those advanced by the GLMD. The first is to reconfigure the site
plan to accommodate the higher water level. This was initially proposed by Ms.
Hohn in a letter to Dune Harbor addressing the pending application: "the
proposed subdivision could be redesigned to utilize the current inland lake
level, thereby eliminating the need to lower the lake level and the need for
the project." Exhibit P-4. Mr. Chandonnet testified it took a period of
two years and the expenditure of $867,500 to plan and obtain approval of the
existing site plan. Mr. Stebbins testified that to now re-do a plan would involve
"starting from scratch", involving, among other things, totally redesigning
home sites, roads, water, sewer, and other utilities. Further, there is no guarantee
it would be approved. As far as costs, he testified such a plan would leave
only 8 lots unaffected and involve a loss of 17 lake front lots, resulting in
lost revenue of $1,725,000. Reducing the size of the remaining lots would result
in a loss of $320,000. The cost of redesigning the project would be some $200,000.
Adding these costs to that already expended, the total cost and lost revenue
involved in a redesign of the project is $3,112,500. T., pgs. 275-277.
All of the witnesses acknowledged this alternative is feasible in that it can
be physically accomplished irrespective of the costs involved. Further, to do
so would alleviate the necessity of the draw down and the outfall. However,
having previously found that the outfall may only cause a material adverse impact
to the dune under the so called "worst case scenario", and finding
later in this PFD that the smaller lake resulting from the draw down is consistent
with Part 301, it would be imprudent to force Dune Harbor to spend additional
millions of dollars, and I so find. Therefore, the proffered alternative, while
feasible is not prudent.
The second alterative suggested by Ms. Hohn is to install "[A] pipe and
an actively pumped system [that] could be designed to discharge directly to
the bottom of Lake Michigan a distance from the shore
." Exhibit P-4.
Ms. Hohn admitted she did not perform any kind of economic analysis, nor did
she attempt to ascertain the length of pipe that would be required to make the
plan viable. She also admitted having no contact with the U.S. Army Corps of
Engineers (COE) on whether it would permit such an occupation of Great Lakes
bottomland. T., pg. 741. Mr. Chandonnet testified that he was advised the project
would cost some $1,500,000 exclusive of the costs of a pump and electricity.
T., pg. 78. Further, in his opinion the COE would not be receptive to such a
proposal. Id. He also expressed legitimate concerns over potential ice damage
and zebra mussels invading the outlet. T., pg. 80. Mr. Dunlop agreed with the
cost estimate and added such a pipe would entail significant maintenance costs
as well. T., pgs. 834-835. Mr. Stebbins testified, in addition to those concerns
that sand shifts could result in sand plugging the outlet. T., pg. 313. Mr.
Bennett testified such a pipe would have to be some 2,000 feet long to get beyond
the bar system to be successful, and that in his experience some underwater
discharges have worked while others have not. T., pg. 493.
As is the case with redesigning the housing development, it is evident a pipe
on Lake Michigan bottomland could be physically accomplished and hence is feasible.
However, to reiterate it has been found that the outfall would only potentially
impact dune in any material way under limited circumstances. Based on that finding,
it would be imprudent to force Dune Harbor to incur the additional cost and
undertake such a project, especially with the inherent risks outlined above.
To state it another way, there is no cogent reason articulated to merit the
considerable additional expenditure for what may prove at best, a high maintenance
facility or at worst, an unworkable one.
Based on the foregoing findings, the ultimate issue is reached: whether the
Petitioner is entitled to a special exception under § 35317(1).
Practical Difficulty
Section 35317(1) provides, as applicable:
[t]he department may issue special exceptions under the model zoning plan if
a local unit of government does not have an approved zoning ordinance, if a
practical difficulty will occur to the owner of the property if the variance
or special exception is not granted. In determining whether a practical difficulty
will occur if a variance or special exception is not granted, primary consideration
shall be given to assuring that human health and safety are protected by the
determination and that the determination complies with applicable local zoning,
other state laws, and federal law....
Part 353 utilizes both the terms "variance" and "special exception".
However, it is clear from the language of §§ 35316 and 35317 that
the term "variance" is applicable to actions of local units of government
under its zoning ordinance. Furthermore, the term "special exception"
applies to an action of the DEQ in the absence of a local ordinance under the
model zoning plan, which occurred here. However, the terms are used synonymously
in this statute.
Other than mandating that primary consideration be given to human health and
safety, and that the project comply with all other applicable laws, Part 353
does not define "practical difficulty". However, it is a legal term
of art commonly utilized in zoning law, allowing the utilization of judicial
construction of the term. The Court of Appeals articulated three factors to
consider in determining whether compliance with zoning regulations will cause
a practical difficulty:
1. Whether compliance with the strict letter of the restrictions governing area,
set backs, frontage, height, bulk or density would unreasonably prevent the
owner from using the property for a permitted purpose or would render conformity
with such restrictions unnecessarily burdensome.
2. Whether a grant of the variance applied for would do substantial justice
to the applicant as well as to other property owners in the district, or whether
a lesser relaxation than the applied for would give substantial relief to the
owner of the property involved and be more consistent with justice to other
property owners.
3. Whether relief can be granted in such fashion that the spirit of the ordinance
will be observed and public safety and welfare secured.
National Boatland, Inc. v Farmington Hills Zoning Board of Appeals, 146 Mich
App 380, 388; 380 NW2d 472 (1985).
The form application for special exception (Exhibit P-2) contains four questions
that closely follow the above test. For instance, questions A and B on the form
state the same inquiry as #1 and #2 of National Boatland. Question C asks whether
the plight of the owner is due to unique circumstances of the property, while
question D asks whether the problem is self-created. These latter two queries
may be interpreted as loosely tied to the substantial justice requirement of
the second prong of the National Boatland test and will be so addressed. Therefore,
the test articulated in National Boatland is utilized as this Tribunal has done
in previous Part 353 cases.
I. Unnecessary Burden
This consideration requires a balancing of the proposed activity against the
unique features of the property. The unique feature of this property is the
unanticipated rise in the level of South Lake, necessitating the project under
review. For the reasons stated, the higher level of South Lake renders implementation
of the existing approved site plan impossible. To deny Dune Harbor the proposed
activity to compensate for that development would prevent its using the property
as it intended and be unnecessarily burdensome and I so find. Feasible and prudent
alternatives are discussed below.
II. Substantial Justice Served
This standard requires a balancing of Dune Harbor's desires against the interest
of other property owners in the area. There was no evidence submitted applicable
to direct impacts on other property owners. The record indicates that the entire
project is confined to Dune Harbor's property, and by Dr. Meadows' estimate
any potential impact of the outfall will not go beyond the extensive frontage
owned by that entity. While an inference may be made that any alteration of
the natural features might lower the aesthetic value of the property to other
owners in the area and the public, this does not equate to a deprivation of
substantial justice.
The GLMD contends Dune Harbor created its own hardship by failing to properly
access the potential ultimate level of South Lake. In support of this contention
it provided evidence that Nugent Sand and specifically Mr. Chandonnet, was aware
of higher groundwater levels. Mr. Chandonnet readily admitted this and testified
to his knowledge of reported groundwater levels of 596 feet in 1980 and 590
feet in 1994. This information was gathered from groundwater monitoring performed
with pziometers installed around the mining site in response to neighbors' concerns
relative to impacts on the water table and their wells. However no hydrological
study of South Lake was performed at either time. As to the level of South Lake,
he testified it historically varied, for the most part, due to ongoing mining
activities. However, it was assumed, when mining operations ceased, that South
Lake would neither meet nor exceed its level of 582 to 584 feet present at the
commencement of mining. T., pg. 118. Mr. Nevedal testified that in his experience,
which covers the commencement of reclamation in 1987 to its completion in 1999,
the highest level he recalled as 584 to 585 feet. T., pg. 170. The GLMD is critical
of Dune Harbor not performing any hydrological studies until the level of South
Lake substantially exceeded historic levels. However, in point of fact, in addition
to the historic levels Dune Harbor relied on the input of Mr. Daniels and Mr.
Hinks.
Mr. Daniels testified that he did not state what the ultimate level of South
Lake might be, but did advise Mr. Chandonnet and more often Mr. Nevedal, that
the level was continuing to rise, but they would not know for some time at what
level the Lake would stabilize. T., pg. 642. Having prepared a sand dune mining
inspection report on March 19, 2001 (Exhibit P-34), he characterized the level
to be the highest he had ever seen. T., pg. 676. Mr. Hinks, a hydrogeologist,
reviewed historical information provided by Dune Harbor and performed groundwater
modeling on the site in 2001. From the data he ascertained the mining activities
had created a water budget deficit for South Lake. He described the process
in his testimony. The highest levels of around 584 would historically be present
in the spring at the start of the mining season. As the mining season progressed,
the level would drop off rapidly and flatten out five to six feet lower. In
November when the mining activity ceased for the year, there would be a quick
rise that would flatten out at the end of winter, again at about 584. This cycle
would repeat itself each mining season. T., pgs. 380-381.
In reference to the rise of South Lake he testified he was surprised when the
level of South Lake rose to 588 after the cessation of mining there. At that
point he started doing what he termed "serious modeling". As part
of that, he reviewed records back to 1999 indicating the annual pattern described
above. Based on this, he testified:
I believe we have recovered full elevation of the lake. I believe the difference
between where we see flattening out towards the end of the non-mining season
versus what's occurred in the last three years shows recharge from two different
sources, rather permeable sediments that are mined and recharge from the lake
from the sides and possibly something deeper, which is-which is pushing this
up over the last couple years, two or three years.
T., pg. 381
From this record it is evident that the rise in the level of South Lake to
592 feet was wholly unanticipated and fortuitous. It is further evident that
Dune Harbor reasonably relied on existing data in its assumption that the level
of South Lake would revert to its original level. It is important to note, too,
that the spikes of 596 feet in 1980 and 590 feet in 1994 were groundwater levels,
not the surface level of South Lake. Therefore, the formulation of the site
plan based on that assumption was reasonable. I find, as a Matter of Fact, that
substantial justice would be served by allowing the draw down of South Lake
as proposed.
III. Relief within the Spirit of Part 353
The "spirit" of Part 353 is articulated in the legislative findings:
(a) The critical dune areas of this state are a unique, irreplaceable, and fragile
resource that provide significant recreational, economic, scientific, geological,
scenic, botanical, educational, agricultural, and ecological benefits to the
people of this state and to people from other states and countries who visit
this resource.
***
(c) The benefits derived from alteration, industrial, residential, commercial,
agricultural, silvacultural, and the recreational use of critical dune areas
shall occur only when the protection of the environment and the ecology of the
critical dune areas for the benefit of the present and future generations is
assured.
MCL 324.35302.
Both Dr. Arbogast and Dr. Meadows, as stated, perceived no adverse impacts of
the outfall under present conditions. While Dr. Meadows alluded to possible
problems at high water levels, the likelihood of the "worst case scenario"
has been previously addressed. Should the level of Lake Michigan reach highs
beyond that of the mid-1980s the damage to the barrier dune complex, along with
the entire shore environment, would be catastrophic, irrespective of the presence
of the outfall on the beach. Mr. Bennett's testimony on this phenomenon is especially
compelling:
A. Even in the 1986 water levels, which were substantially lower than that,
there were catastrophic failures of the bluff faces, sand dune collapses, a
number of homes went in, shore protection failed, groin systems emptied out,
erosion occurred behind them.
Q. You say it did affect shoreline structures as well?
A. Oh, yeah.
Q. What kind of structures are you talking about?
A. Groins, seawalls, revetments.
Q. And under those conditions, Mr. Bennett, would any of the proposed outfall
structures here have any additional material impact on the shoreline.
A. It would be hard to separate the impact of the structure at that point from
the natural-occurring erosion, very difficult, because it would be so catastrophic.
In fact, the structures would probably get cut behind both of-behind them, and
they'll probably potentially fail also.
T., pg. 1107
In the final analysis, based on this record, the alteration of the dune proposed
would have no appreciable adverse effects on the environment and ecology of
the critical dune area. Therefore, the benefits outlined in the above legislative
findings to the people, present and future is assured.
Having found that on this record there are no feasible and prudent alternatives
to the pipe and outfall, the various configurations of that activity must be
addressed.
The Alternative Designs
In what is fairly characterized as an evolutionary process, Dune Harbor considered
numerous designs of the outfall. Three designs were placed into evidence and
are depicted in Exhibit P-24. Mr. Stebbins explained the designs appear to be
somewhat different than the original submittals in that the orientation and
datum of each was altered to be consistent in order to allow accurate comparison.
The designs are as follows:
1. This is the initial proposal, and was prepared by Mr. Stebbins and Mr. Bennett.
It involves an outfall with a plunge pool approximately 55 feet long and 35
feet wide. At the base are 3 ton stones placed over erosion control fabric,
edged with 200 to 1,000 pound stones to match the existing grade. The purpose
of the design is to dissipate the energy of the water discharge to prevent erosion.
2. This proposal, labeled Revision #4, is similar to #1. The primary revision
is its substance. The plunge pool is reduced to 42 feet wide, but 63.5 feet
long. While both of these plunge pool designs would be installed below grade,
this design is dug deeper into the beach with a 12-inch layer of bedding stone
over erosion control fabric topped and edged with 200 to 1,000 pound stone.
This design was proffered in response to the GLMD staff's concerns over the
original designs ability to withstand the natural forces of ice and storms.
3. The third design was suggested by Mr. Jannereth during the review of the
application for special exception. It is essentially a revetment 15 feet long
and 28 feet wide. This design has the highest elevation above the OHWM at approximately
586 feet, or 4 feet above the highest recorded water level for Lake Michigan.
While this design would greatly decrease the probability of water reaching it,
the design would not dissipate as much energy from the water discharge resulting
in a small channel through the foredune into Lake Michigan. Dr. Arbogast testified
this channel or erosion would be insignificant due to the ephemeral or transient
nature of the foredune, which he did not consider to be "very noteworthy
in terms of their geology". He was asked:
Q. If I understand you, you're saying that this foredune complex is going to
change shape on it own regardless of whatever may be there?
A. That's right.
Q. Whatever structure might be placed there?
A. That's right. You can't say the same thing, though, for the barrier dune
ridge. That's a very different system.
T., pgs. 1089-1090.
Any of the designs would require maintenance and during periods of low water
levels or low precipitation the installation may become covered by sand. Ice
could cause some stone movement. In higher water levels some erosion might occur
around the installation. That being said, none of these eventualities would
present a situation that could not be rectified. The record indicates Dune Harbor's
willingness to install any of the three designs, although the original would
be preferred.
Based on Dr. Arbogast's testimony that there would be no significant impact
to the foredune complex regardless of which of the three installations was built
and the unlikely probability of any impact to the barrier dunes, from an environmental
perspective any would appear acceptable. However, although minimal, the revetment
(#3) would cause, to some degree, more erosion or channeling than the others.
Regarding either of the two plunge pool designs (#1 and #2) Mr. Bennett testified
he saw no "measurable degree" of impact to the dune. T., pg. 475.
Mr. Dunlop testified the ultimate expected base flow (after the initial drawdown)
would be 1.2 feet per second. At such a low rate he would not expect erosive
effects. He also noted that the volume of water drawn from the lake and discharged
to the pipe could be controlled so as not to exceed 1.2 feet per second. T.,
pgs. 829-830.
The GLMD argues none of the three designs should be allowed. The basis of that
argument is summarized on page 3 of the GLMD's Closing Argument: "As Lake
Michigan rises, the waters in the subject man-made lakes will correspondingly
rise, creating the need to release increasing volumes of water from the inland
lakes and through the outfall pipeline, in order to accomplish Petitioner's
goals." Quite simply, the record does not support this assertion. In fact,
the evidence is to the contrary, as indicated in Mr. Daniel's inspection report
of March 19, 2001, where he states under general comments:
The South Lake is at or very near what should be it's normal high stand. This
elevation does NOT seemed (sic) to be directly controled (sic) by Lake Michigan
elevations - since this "high stand (sic) was last observed in 1988 or
1989 - when Lake Michigan was high - and now it has come back to this elevation
when Lake Michigan is at a 50 year + cyclic low. Appearently (sic) the gradient
between the lakes will merely steepen or flatten to accomadate (sic) the differences.
There must be some change in aquifer characteristics downgradient or some "sealing"
of the south lake bottom to account for this high of an elevation to be so independent
of Lake Michigan controls.
Exhibit P-24.
Mr. Hinks attributed this phenomenon to something akin to the effect of an
artesian well:
An artesian well will have a higher water level in it than the shallow water
- groundwater surrounding it. In cross section, if you look at the present site
and the lake levels, it's almost - that's the topography and you have the lake
and then it drops off into Lake Michigan. The water table comes in, and it's
quite striking how it drops off down toward the lake. If you were just - generally
a lake reflects kind of an average groundwater elevation between the upgradient
side and the downgradient. This is much closer to the upgradient side than the
downgradient and needs that extra source, I believe, to bring it to that level.
T., pg. 384.
Based on this record, there is no demonstrated risk that the inevitable higher
levels of Lake Michigan during those cycles will affect the level of South Lake,
and consequently increase the volume of water through the outlet system. Regardless,
as stated by Mr. Dunlop, the outflow can be controlled to not exceed 1.2 feet
per second. This, of course, would also serve to control climatic variances.
Next, the issue of which of the three proposed outfalls is the most appropriate
must be determined. The general effects of any outfall on the dune and the particular
characteristics of each have been outlined above. To cut to the chase, I find
that the design identified as #3 should be employed. There are a number of reasons
for reaching this conclusion. It is smaller in size than the others, and even
though none of the designs would present a material adverse impact, a smaller
size would present the least impact. The smaller size may present a risk of
more erosion in that there is less area to diffuse the flow. However, once the
flow reaches the design level there is little or no risk of erosion of any lasting
effect because the dune and beach comprise a dynamic system constantly being
moved by wind and wave action. Its elevation of 586.7 feet would according to
Mr. Bennett, avoid the perils set forth under Dr. Meadows' so called "worst
case scenario." Another factor that cannot be ignored is the fact that
design #3 was proposed by the GLMD, in the person of Mr. Jannereth, as a possible
alternative. Obviously, that alternative was not permitted, mainly because the
GLMD took the position that the outfall constituted a "structure"
and was absolutely forbidden in the location proposed. This Tribunal has for
the time being, rejected that argument. In sum, the GLMD having proposed that
design, at least as a possibility, and Dune Harbor being willing to employ it,
coupled with the finding as to a lack of adverse impact to the resource, support
the conclusion it should be permitted, and I so find, as a Matter of Fact.
CONCLUSIONS OF LAW - PART 353
Based on the findings of fact set forth above, I conclude, as a Matter of Law:
1. Dune Harbor Estates, LLC is the proper applicant for a permit and the processing
of the application for a permit was procedurally correct.
2. The proposed activity is a use as the term is defined in Part 353. MCL 324.35301(j).
3. No feasible and prudent alternative location or method to accomplish the
benefits expected from the use to minimize the impact to the dune has been established
on this record. MCL 324.35316(1)(g)(i) and (ii).
4. Dune Harbor Estates, LLC, has demonstrated a practical difficulty sufficient
to merit a special exception for the project as modified by the utilization
of the outfall configuration found to be appropriate. MCL 324.35317(1); National
Boatland, Inc. v Farmington Hills Zoning Board of Appeals, 146 Mich App 380;
380 NW2d 472 (1985)
PART 301 ANALYSIS
Section 30106 provides the prerequisites to issuing a permit:
The department shall issue a permit if it finds that the structure or project
will not adversely affect the public trust or riparian rights....
MCL 324.30106.
It has been previously determined in the June 24, 2003 Order that since the
water bodies are neither impressed with the public trust nor subject to riparian
rights, there can be no impacts thereon. However, beyond addressing those considerations,
§ 30106 provides the following standards for the review of an application
submitted under its authority:
In passing upon an application the department shall consider the possible effects
of the proposed action upon the inland lake or stream and upon the waters from
which or into which its waters flow and the uses of all such waters, including
uses for recreation, fish and wildlife, aesthetics, local government, agriculture,
commerce and industry.
MCL 324.30106.
Recreation
As a preface, it is undisputed that the proposed development contemplated around
South Lake will provide recreation in the nature of swimming, boating, and fishing
to the residents. Beyond that obvious conclusion is the impact to the resource
if the level of South Lake is lowered. To evaluate the impacts of the proposal
on the aquatic resources of South Lake, Dune Harbor retained Mr. Kogge. The
major part of this testimony and his qualifications are recited in the analysis
of the impacts on fish and wildlife later in this PFD. Relative to recreation,
from his review of the plans, previously designed by Robert Leighton and Associates,
as well as his own on site reconnaissance, he determined that South Lake was
designed for recreation with shallow 8 percent slopes to facilitate a safe non-motorized
boating and swimming environment. T., pg. 878. A number of photographs demonstrate
South Lake has a hard sand bottom and good quality water. Exhibits P-27A-I.
Under the current level of South Lake some of the shallow water and safe contours
of the lake have been eliminated, thereby diminishing recreational activities
from that which would result if the level is lowered. Specifically, Mr. Kogge
testified the elevated water level has inundated the 32 percent landward slopes
required for reclamation by the GLMD, thereby creating a steeper and less safe
near shore area. T., pg. 883. In sum, restoration of the anticipated lower level
would restore the recreational potential and values envisioned.
Fish and Wildlife
The primary objection of the GLMD revolves around the impact of lowering the
water level on the littoral zone. The sole witness for the GLMD is this regard
is Mr. Fortney. In his testimony, he basically reiterated the language of the
denial letter of April 9, 2003, which, as pertinent, stated:
The proposed lowering of the water level within the inland lake(s) below the
natural level will result in the destruction of more than 30 acres of shallow
water (littoral zone) habitat. This habitat is critical to the fishes and aquatic
communities that have developed in the subject lakes(s).
Exhibit P-3.
When Mr. Fortney was asked whether anything he had heard during the course
of the hearing to that point would alter his opinion, he stated:
I have heard at least what I could characterized as rumor that the-an agent
for the applicant has done a little more investigation and is suggesting that
the shallow slopes in the submerged portion of the lake are actually at an offshore
location now as a result of the higher water levels and there may, in fact,
be an increase in littoral zone habitat or shallow water habitat if the lake
is lowered. I was intrigued by that. And if it happens to be true, I would believe
it certainly. T., pg. 765.
The "rumor" referenced by Mr. Fortney was the opinion of Dune Harbor's
agent Mr. Kogge, who testified after Mr. Fortney. Mr. Kogge has a Masters Degree
from Michigan State University in fisheries and aquatic biology. In June 2003,
he assessed, on behalf of Dune Harbor, the resource values of both North and
South Lakes. In that capacity he initially reviewed existing documentation,
including surveys, correspondence and existing permits. Then he and Mr. Stebbins
boated around South Lake and walked its shoreline to assess the fisheries resources,
specifically the shore slopes and contours that encompass its littoral zone.
As a result of his study he came to an opinion that consists of two parts. First,
by reducing the size or area of the lake by approximately 12 acres, the carrying
capacity or number of fish the lake could sustain will necessarily be reduced.
He perceived this result as a detriment to the resource. However, because the
elevated level of the lake has reduced the zero to six-foot shore contour as
designed in the reclamation project, lowering the level will restore the most
productive area of the lake: the shallow littoral zone.
Regarding wildlife, Mr. Chandonnet described South Lake as a "thriving
wildlife habitat" with the presence of ducks, geese, swan, and cormorants.
T., pg. 137. None of the witnesses presented by the GLMD directly addressed
wildlife impacts. The sole reference to wildlife came during Mr. Fortney's testimony
as to whether he thought a reduction in fisheries and wildlife habitat in South
Lake would result in impairment or destruction of natural resources of the state
as defined in 1999 MR 6, R 281.811(g)(iii). T., pg. 770. The sole substantive
testimony regarding wildlife came from Mr. Kogge. In his opinion, lowering the
level of South Lake would have an adverse effect on wildlife. With the present
elevation, the trees that have come in along that 32 percent slope are now underwater.
This serves to provide some structure and habitat for waterfowl. The submerged
vegetation that is now under water. T., pg. 894.
Having made these overall assessments as to both fish and wildlife, and being
asked whether he thought there would be anything more than minimal impacts to
the environment, Mr. Kogge concluded that any adverse impacts would be minimal
and would, in fact, enhance some resources. Because lowering the level would
create a greater distance of the zero to six-foot near shore contour that resource
would be enhanced. Even though the acreage of the water body would decrease
the creation of a better quality shallow water habitat outweighs the loss of
area. T., pgs. 897-898.
In sum, we are left with a record where only Mr. Fortney and Mr. Kogge addressed
this criteria. As noted, Mr. Fortney frankly stated that if Mr. Kogge testified
as rumored and that testimony was true, he would believe it. Mr. Kogge's opinion
regarding fish is credible and essentially unrebutted. As to wildlife, Mr. Kogge
perceived a minimal detriment, and he concluded that after balancing those detriments
against the benefits that would result if the level of South Lake was lowered,
the overall effect of the project would be positive. Again, this opinion is
essentially unrebutted. Based on this record, I find as a Matter of Fact, that
the net effects on fish and wildlife will be positive.
Aesthetics
Mr. Kogge testified the proposal would enhance aesthetics by providing the development
as planned in respect to the lot sizes, lake contours and appearance. He noted
under the current conditions many of the plantings and trees are inundated and
that lowering the water level would restore them to their original intended
appearance. In general, GLMD would prefer a re-worked plan that would result
in less building sites and, therefore, less general intrusion. It would also
prefer not to have the outlet on the beach.
In the end this is a necessarily subjective criteria because aesthetics are
literally in the "eyes of the beholder". Having said that, there is
nothing in this record to support a finding that any portion of the proposal
would be so out of character with the area as to render it unaesthetic. It is
evident that the residential development will be comprised of high end homes
on or near a high quality lake. The outfall will not be so obtrusive as to negatively
alter the general aesthetics of the beach area. I find, therefore, that aesthetics
will not be adversely affected.
Local Government, Agriculture, Commerce, and Industry
There is no evidence of any present or potential use of the lakes, which are
entirely owned by Dune Harbor, by local government or agriculture. There is
also no evidence of any past, present, or future commercial or industrial uses
that would be affected, other than the sand mining activities of Dune Harbor's
parent company, Nugent Sand. Naturally, any impact to that entity would be welcomed
by it given the common ownership.
Finally, § 30106 prohibits the DEQ from issuing a permit "if the
proposed project or structure will unlawfully impair or destroy any of the water
or other natural resources of the state." To implement this provision the
DEQ promulgated 2000 MR 8, R 281.814:
In each application for a permit, all existing and potential adverse environmental
effects shall be determined and the department shall not issue a permit unless
the department determines both of the following:
(a) That the adverse impacts to the public trust, riparian rights, and the environment
will be minimal.
(b) That a feasible and prudent alternative is not available.
>Subsection (a) requires that the impacts to the public trust and riparian rights
will be minimal. It has previously been found that South Lake is neither impressed
with the public trust nor subject to riparian rights. Therefore, there can be
no impacts thereon. Environmental impacts have been previously addressed under
specific criteria.
Subsection (b) requires a finding that no feasible and prudent alternatives
exist. It has been previously found there is no feasible and prudent alternative
to the activity proposed.
<>CONCLUSIONS OF LAW
Based on the findings of fact set forth above, I conclude, as a Matter of Law:
1. The activity is proposed to occur on bottomlands of an inland lake. MCL 324.30101(a),
(f) and (i).
2. The proposed activity is regulated under Part 301. MCL 324.30102.
3. The proposed activity will not adversely affect the public trust or riparian
rights. MCL 324.30106.
4. The proposed activity will not adversely affect the inland lake, the waters
from which or into which waters flow, or the uses of the lake enumerated in
MCL 324.30106.
5. Having considered the possible effects of the proposed action upon the subject
inland lake and the uses of those waters, the proposed project will not unlawfully
impair or destroy any of the waters or natural resources of the state. MCL 324.30106.
6. The impacts to the environment will be minimal and there are no a feasible
and prudent alternatives. 2000 MR 8, R 281.814.
PROPOSAL FOR DECISION
Based upon the Findings of Fact and Conclusions of Law, it is proposed that
a Final Order be entered GRANTING a special exception under Part 353 to Dune
Harbor Estates, LLC, for an outfall as depicted in the third configuration for
the outfall depicted in Exhibit P-24 (copy enclosed). It is further proposed
that a Part 301 permit be issued as applied for.
Dated: February 24, 2004 __________________________
Richard A. Patterson
Administrative Law Judge
|